"Applications of GT STRUDL on Boston's Central Artery / Tunnel Project Congress Street to North Street"


by
Paul F. Harrington, P.E.
&
James R. Branch, P.E.
Fay, Spofford & Thorndike, Inc.
Burlington, MA


Abstract

A major component of the Central Artery/Tunnel Project is the depression of the existing 6-lane viaduct (Interstate I-93) up to 90 feet below grade through the heart of downtown Boston.  Since the new tunnel is located directly below the existing viaduct, a steel underpinning system was designed to support the structure and allow removal of the existing foundations located within the new tunnel alignment. GTSTRUDL was used to design the underpinning and to analyze the effects of transferring the 50 year-old structure from the existing "rigid" foundations onto the flexible underpinning system while the roadway remained open.  Slurry walls are used for support of excavation during construction of the cut-and-cover tunnel, support of the existing viaduct underpinning and also serve as the permanent tunnel walls.  This required that the analysis and design of the walls account for all of the excavation, bracing and tunnel construction stages in addition to loads applied to the completed tunnel.  GT STRUDL was used to perform an incremental non-linear analysis that included the entire history of internal stresses in the wall due to all stages of construction.

Underpinning Analysis

The primary objective of the underpinning system was to maintain the structural integrity of the existing steel viaduct while clearing the corridor for construction of the new tunnel below.  The underpinning system replaces the existing, "rigid" pile foundations with "flexible" grade beams, which span the excavation.  The inherent non-linear behavior associated with changing an active structures' boundary condition created the need for a staged analysis.GT STRUDL was used to perform a linear displacement analysis of the underpinning system.
 
The model accounted for the jacking and load transfer operations, such that the stress redistribution within the existing rigid frame was accurately assessed.  The MEMBER DISTORTION command was used to accurately model the jacking displacement applied to the underpinning system.  In addition, the results of the model were vital during the actual jacking and load transfer (column cutting) operations that were performed under live traffic.  The predicted load/displacement correlation allowed Engineers to closely monitor the jacking increments and make timely adjustments, if necessary.

Incremental Non-linear Analysis of Slurry Walls

Since the slurry walls used for excavation support also serve as the permanent tunnel walls, a staged construction analysis of the deep braced excavation was required in order to account for residual stresses which are "locked" into the walls at the end of the final construction stage.  Using the Beam on Elastic Foundation method combined with GT STRUDL's NONLINEAR capabilities, structural models were developed which simulated the changing loads and boundary conditions that occur during the excavation and construction stages.
 
A single input file was created that included all of the structural elements that would be used in the analysis, and by using the CHANGES and DELETE commands, the boundary conditions and loads were adjusted for each stage of construction.  Then, the NONLINEAR ANALYSIS CONTINUE command was used to produce member force results for each stage.

Biographical Data

Paul F. Harrington, P.E.  is a Vice President at Fay, Spofford and Thorndike, Inc.  Paul has been with FST for 19 years and has worked on a variety of heavy civil transportation projects.  Most recently, he has been heavily involved with the ongoing construction over $1B of tunnel construction as part of Boston's Central Artery Project.

Education

B.S.C.E.    University of Massachusetts

Biographical Data

James R. Branch, P.E.  is a Senior Principal Engineer with Fay, Spofford & Thorndike, Inc. located in Burlington, Massachusetts.  He is currently Structural Task Manager for the FST/HNTB Central Artery joint venture team and has over 15 years experience on heavy construction projects including tunnels, wastewater treatment facilities and waterfront structures.

Education

B.S.C.E.    State University New York (SUNY) at Buffalo